Home > Questions typically asked of a civil engineer during a viva examination... Author: Engr. Dibakar Dey, IIT-Kharagpur, India.

Questions typically asked of a civil engineer during a viva examination... Author: Engr. Dibakar Dey, IIT-Kharagpur, India.

1. Please, have a seat. May I have your name?

Answer: Thank you, sir.

Md. -----------

2. Where are you currently working?

Answer: Geo-Science Engineering Inspection Service, Jatrabari, Dhaka.

3. What are your responsibilities there?

Answer: Project supervision and office management.

4. Well, could you tell us something about yourself?

Answer: Sir, my home district is Chandpur. I completed my SSC in 1999, my diploma in 2003, and my BSc in 2010. I currently reside in Dhaka.

5. What kind of work are you particularly good at?

Answer: Both structural and finishing work, sir.

6. We are looking for someone for structural work.

Answer: That’s fine, sir.

7. Have you worked on structural projects before?

Answer: Yes, sir.

8. Can you perform layout work?

Answer: Yes, sir.

9. If a building layout has been provided, what aspects would you check?

Answer: When checking a layout, I would first consult with the person who prepared it to understand their starting point. Next, I would verify the grid line measurements and check the diagonal dimensions. I would also examine the setbacks. If everything is in order and if the project involves piles I would then verify the pile point locations.

10. Could you tell me which types of foundations are most commonly used nowadays?

Answer: Currently, shallow foundations and deep foundations are the most frequently used types.

11. Can you explain what deep foundations are?

Answer: Yes, sir.

12. Have you worked on piling projects?

Answer: Yes, sir, I have.

13. What is the minimum cutting length for a 20-inch pile?

Answer: A minimum of 19 inches.

14. Can you name the equipment used for piling work?

Answer: Tripod (or frame), chisel (or cutter), funnel, hopper (or bucket), drilling rod, tremie pipe, concrete mixer, welding machine, winch machine, water pump, etc.

15. What should be checked in a reinforcement cage?

Answer: For a reinforcement cage, one must verify the diameter, rings, spacing, joints, lapping, height, and welding all in accordance with the design specifications.

16. Why do we use piles?

Answer: When the load from a building exceeds the soil's bearing capacity—as determined by a soil test—we use piles to create a deep foundation, transferring the load to a stronger, deeper soil stratum.

17. Have you reviewed the soil test report?

Answer: Yes, sir, I have.

18. What information does the report contain?

Answer: It includes details on soil type, groundwater level, and SPT (Standard Penetration Test) values.

19. What is SPT?

Answer: SPT stands for Standard Penetration Test.

20. Why is 'washing' (flushing) performed in a pile bore?

Answer: It is done to clear out the mud/clay from within the borehole.

21. How much time is allowed?

Answer: 30 minutes is the specified duration, but it is better to continue until the water runs clear.

22. Why is a higher slump value used for the concrete mix for piles?

Answer: To prevent the concrete mix from absorbing water, as the water present in the borehole is often dirty or contaminated.

23. How long after the completion of a pile can it be broken down (trimmed)?

Answer: 28 days.

24. Can you explain why it needs to be broken down?

Answer: During the concreting process, mud and soft soil from the bottom of the pile rise to the top, which weakens the concrete at the pile head; therefore, this portion must be removed. Additionally, the reinforcement bars (rebars) at the pile head need to be bent to create a connection with the foundation. Generally, we break it down to the level of the bottom of the pile cap, but in practice, it must be removed until sound, solid concrete and exposed reinforcement bars are reached.

25. What is the concrete cover for the pile?

Answer: 3 inches.

26. What should you check before pouring concrete for footings and pile caps?

Answer: Before pouring concrete for footings and pile caps, you should check the following: the integrity of the shuttering (formwork) and whether there are any gaps; the connection (binding) of the footing reinforcement with the pile reinforcement; the spacing of the reinforcement bars; the diameter of the bars as per the design; the condition of the joints; and ensuring that any weak or loose concrete on top of the pile cap has been removed.

Most importantly, you must ensure that the center of the column aligns with the center of gravity (CG) of the pile cap.

27. What is the required concrete cover for columns, beams, and slabs?

Answer: Column: 1.5 inches; Beam: 1.5 inches; Slab: 3/4 inch.

28. Which reinforcement bars—those in the short direction or the long direction—should be placed first?

Answer: In footings, long bars are placed first, followed by short bars; in slabs, short bars are placed first, followed by long bars.

29. What should be checked before pouring concrete for columns, beams, or slabs?

Answer: Check the shuttering (formwork), leveling, bracing (props/bamboo supports), concrete cover, bar diameter, spacing, and ensure there are no gaps or openings.

Part 1: (Try answering these yourself first, then check the answers.)

1. Why is gypsum added to cement?

2. What are the dimensions of the cube used for testing the strength of concrete?

3. For a water-cement ratio of 0.45, how many liters of water are required per bag of cement?

4. What is laitance?

5. What is used to perform a slump test?

6. What are the top and bottom diameters of the slump cone?

7. What is the height of the slump cone?

8. By what percentage does the strength of concrete decrease if it contains 5% voids?

9. For a cylinder used to test the strength of concrete, what is the ratio of its height to its diameter?

10. What are the dimensions of the cylinder used for testing the strength of concrete?

Answers:

1. Gypsum is used to delay the setting time of cement.

2. 15 cm × 15 cm × 15 cm.

3. 22.5 liters.

4. If the water content in concrete is too high, cementitious material accumulates on the surface, forming a white layer known as "laitance."

5. By using a slump cone.

6. Top diameter 10 cm and bottom diameter 20 cm.

7. 30 cm.

8. 30%.

9. Double.

10. Diameter 15 cm and height 30 cm.

Part - 2

1. What is the thickness of a lintel?

2. What is the height of a parapet wall?

3. What is the thickness of the DPC (Damp Proof Course)?

4. What is the thickness of the plaster on the ceiling?

5. How many cubic meters is one bag of cement equivalent to?

6. How much space does one bag of cement occupy?

7. What is the thickness (in cm) of a waterproof roof (terrace waterproofing/mud-phuska layer)?

8. What are the dimensions of a door/window frame?

9. What is the formula for calculating the weight of an M.S. (mild steel) rod?

10. What is the weight of one cubic meter of M.S. (mild steel) rod?

Answer:

1. 15 cm

2. One meter

3. 2.5 cm

4. 6 mm

5. 0.033 cubic meters (1.25 cubic feet)

6. 0.3 square meters

7. 7.5 cm

8. 10 × 8 cm

9. D²/162.2 (D = diameter of the rod)

10. 7850 kg or 78.50 quintals

Part - 3

Consider the following questions regarding roads:

1. What is meant by 'Right of Way'?

2. What factors are taken into account when determining the 'Right of Way'?

3. What is the standard side slope (lateral slope) considered for roads?

4. What is a 'berm'?

5. What is a 'shoulder'? What is its typical width?

6. What is the minimum width for a footpath?

7. How much space (in meters) is allocated for vehicle parking?

8. What is a 'median strip'?

9. What is a 'borrow pit'? What should be the distance of a borrow pit from the road?

10. What is a 'spoil bank'?

11. What is the weight of the roller used to compact the subgrade?

12. What is the thickness of the sand layer applied to the subgrade?

13. What is the thickness of the sub-base?

14. What is the thickness of the formwork (molds) used during the pouring of concrete?

15. How long after the concrete is poured should the formwork be removed?

16. What is the mix ratio of the concrete used?

17. For how many hours should the concrete be cured after pouring?

18. What is a bituminous road?

19. At what thickness should stone chips be spread over a prime coat, and what is the size of these stone chips?

20. How many kilograms of bitumen should be applied per 100 square meters for a prime coat?

21. What is the temperature required for heating bitumen?

22. How many kilograms of bitumen should be applied per 100 square meters for a tack coat?

23. What is a seal coat?

24. What size of stone chips is used in a seal coat?

25. How many kilograms of bitumen should be applied per 100 square meters for a seal coat?

Part - 4

1. How many parts does a building consist of, and what are they? (Two parts: substructure and superstructure.)

2. What are the components of a substructure and a superstructure?

3. What should be the height of the plinth? (45 cm – 60 cm)

4. At what height should windows be placed? (70 cm – 80 cm)

5. Where are skylights, fanlights, sunlights (clerestory windows), sunshades, and cornices used?

6. What is a ventilator? Why is it used?

7. What are a sill and a jamb?

8. What are the bearing and depth of a lintel? (Bearing: 10 cm; Depth: 15 cm)

9. What are the dimensions of sunshades and cornices? (Sunshade: 30 cm – 45 cm; Cornice: 45 cm – 60 cm)

10. What is a 'water-roof' (water-proofing/protective roof layer)? What is its thickness? (Thickness: 7.5 cm)

11. What is a parapet wall? Where is it built? (A wall that is built around the roof)

12. How high is a parapet wall built? (75 cm. – 90 cm.)

13. What is a coping? Where is it built? (Above the parapet wall.

Part - 5

1. What are a tread and a riser?

2. What is a flight? What are the minimum and maximum number of steps in a flight? (Minimum 3 and maximum 15)

3. What are the dimensions of a tread and a riser? (Tread: 22.5 cm – 30 cm; Riser: 12 cm – 19 cm)

4. What is a nosing, and what are its dimensions? (1 inch to 1.5 inches)

5. What is a soffit? (The slab of a staircase is called a soffit.)

6. What is headroom, and what is its required height? (2.10 meters)

7. Within what range of degrees should the slope (pitch) of a staircase be? (Between 25° and 40°)

8. What should be the width of a staircase for residential and public buildings? (90 cm and 1.5 meters)

9. What are quarter-turn stairs and dog-legged stairs?

10. What is the method for determining the number of treads and risers?

11. What is the relationship between a tread and a riser?

12. What is a foundation? What is the function of a foundation?

13. What are shallow foundations and deep foundations? How many types are there, and what are they?

14. State Rankine’s formula for determining the depth of a foundation.

15.1. The amount of waterproofing admixture (such as Pudlo) for DPC should be 5% of the weight of the cement—that is, 2.5 kg per bag of cement.

15.2. The weight of one cubic meter of M.S. (mild steel) rod is 7,850 kg, or 78.50 quintals.

15.3. The weight of one bag of cement is 50 kg, and its volume is 0.0347 cubic meters.

15.4. The weight of one bag of white cement is 40 kg.

16. For residential buildings, the habitable area should be 50%–56% of the plinth area.

17. The number of bricks required for end-edging per running meter is 1 / 0.127 ≈ 8 bricks.

18. For one cubic meter of aggregate (khoa), 320 bricks are required for small-sized aggregate, and 300 bricks for large-sized aggregate.

19. For the transport of construction materials, the horizontal transport distance is 30 meters, and the vertical lifting distance is 1.5 meters.

20. For compression bars, the lap length is 24D without hooks and 44D with hooks; for tension bars, the lap length is 30D without hooks and 60D with hooks.

21. The ratio of brick aggregate (khoa), lime, and brick dust (surkhi) for roof waterproofing (lime concrete terracing) is 7:2:2.

22. The minimum width of a septic tank is 60 cm, and the minimum liquid depth is 1 meter.

23. The minimum diameter of a soak well is 90 cm, and its depth is 1.5 meters measured from the invert level.

24. A culvert has a span of less than 6 meters, while a bridge has a span of more than 6 meters.

25. The slab of a bridge is called a deck slab.

26. Standard lengths of corrugated iron (CI) sheets are 1.80, 2.20, 2.50, 2.80, and 3.20 meters; the width is 0.80 meters, and the depth of the corrugation is 18 mm.

27. The weight of one meter of M.S. (mild steel) angle = 0.00785A kg.

28. A one-ton truck can carry 20 bags of cement on a paved road.

29. A one-ton truck can carry 333 bricks on a paved road.

30. A one-ton truck can carry 13.33 bags of cement on an unpaved (kacha) road.

Part: 6

Clear cover for main (reinforcement) bars:

1. Footing: 50 mm

2. Raft foundation (top): 50 mm

3. Raft foundation (bottom/side): 75 mm

4. Strap beam: 50 mm

5. Grade slab: 20 mm

6. Column: 40 mm

7. Shear wall: 25 mm

8. Beam: 25 mm

9. Slab: 15 mm

10. Flat slab: 20 mm

12. Retaining wall: 20/25 mm (against earth)

13. Water-retaining structure: 20/30 mm

14. Cast-in-situ pile: 50 mm (for 450/500 mm diameter piles), 600 mm diameter piles

 

 

 

 

 

 

 

Department: 
Civil Technology [1]
Powered By : Authority, Bhola Sadar Polytechnic Institute
Planned & Implemented By : Authority, Bhola Sadar Polytechnic Institute