Steel Building Erection: From Start to Finish. Author: Engr. Dibakar Dey, IIT-Kharagpur, India
Work on steel buildings requires extreme precision; all tasks, designs, and drawings are executed in millimeters, as even a minor error can lead to significant mistakes. Compared to RCC (reinforced cement concrete) construction, steel building construction demands much greater precision, necessitating heightened caution during the erection process.
I will now discuss some key points regarding the various stages of steel building erection.
Steps to take before starting work on a steel building:
1. Drawing
Before the erection of a steel building, precise drawings must be prepared in accordance with the design, ensuring there are no omissions. The drawings must be highly detailed, containing all necessary information.
2. Drawing Approval
Once the drawings are prepared, they must be approved by the client. This prevents complications during construction and ensures that no changes occur outside the scope of the approved drawings. Regardless of the project's scale, obtaining formal approval is mandatory; implementing changes midway through a project creates significant difficulties.
3. Safety on the Job Site
Before commencing work, safety protocols must be strictly maintained on the job site. In the construction of steel buildings, components such as columns, beams, rafters, and other structural elements are extremely heavy, and the nature of the work involves significant risk. Therefore, everyone from laborers to engineers must adhere to safety standards while working.
Furthermore, maintaining safety on the job site is not limited to steel building projects alone; it is a requirement for all construction projects.
4. Preparing the jobsite.
1. Before starting work, the jobsite must be cleared; all debris, waste and various obstacles must be removed.
2. Any holes or depressions must be filled, and in hilly areas, the ground must be leveled (excavated/cut) as required.
3. A power supply must be available; it should be checked to ensure a proper and consistent flow of electricity so that no issues arise during the work.
4. Adequate accommodation must be provided for laborers and engineers; furthermore, designated storage areas for materials must be established to ensure safety and security.
5. Sufficient space must be available for the movement of materials, and proper arrangements must be made for the loading and unloading of materials.
6. Space must be allocated for the placement and movement of cranes and other machinery.
From the start of steel building construction:
Following site preparation, the construction phase begins starting with the foundation.
1. Step 01: Foundation Work
2. At the very beginning, ground preparation must be carried out. The ground level should be properly prepared and thoroughly compacted.
3. Subsequently, foundation work must commence in accordance with the design drawings and the soil report.
4. Once the foundation work is complete, the anchor bolts must be installed. Great care must be taken to ensure that both the anchor bolts and the base plates are set at the correct level. Failure to do so will cause difficulties during the subsequent installation of the columns, potentially resulting in the columns being positioned at an incorrect (crooked) angle.
Anchor bolts for Steel Structure(Details):
Anchor bolts are used as connection between Steel column attached to reinforced concrete foundation.
The connection is made by an assembling of different components
1.Anchor bolts
2.Steel plates(Base Plate)
3.Stiffeners.
#Loads [1]
Anchor bolts transfer load as
1.Tension forces
2.Shear forces.
#Types [2]
Type of anchors commonly used
1.Cast-in-place
2.Post-installed
3.Mechanical Expansion bolt
4.Chemical bolt
Cast in place:
Cast in place bolts are used in wet concrete. They can be bolts or hooked bars. Hooked bars are a type of anchor bolts that is used for base plates loaded axially. Cast in place bolts are the strongest but their use maybe a little difficult. Common applications include heavy machines mounted on concrete and connecting foundation to the wall of a building.
Post-installed:
These ones are used after the concrete has set. Their application is not very common
Chemical anchor bolt:
Chemical anchor bolt placed towards the edge of concrete substrates and through masonry block.
Generally its used in set concrete Floor.
he non-expanding nature of a chemically-held rod drastically reduces the chance of the surrounding concrete cracking
Mechanical Expansion bolt:
Expansion bolts can be used to take heavy load.Generally it is used in walls .
By tightening the bolt, the nut on the opposite end pulls into the shell, expanding it outward and wedging it inside the hole in the wall.
It can handle both vertical and horizontal loads.




Anchor bolts are an important component of steel buildings. Typically, steel columns are connected to them; the anchor bolts are embedded within the RCC (reinforced cement concrete) columns and the steel columns are then attached to them using nuts and bolts.
The specifications for the anchor bolts are provided below.
Anchor Bolt: >Typically has a diameter of 20–30 mm
>Has a length of 80–100 mm
>Extended length: at least 350 mm into the concrete
>Material: Galvanized mild steel
>Origin: China/Belgium

1. Step 02: Framing Work
2. Framing begins after the anchor bolting and base plate setup. All materials for the framing are fabricated at the factory; they arrive at the site as ready-to-install components.
3. For the framing process, the columns must be set up first a task that requires great care. It is also essential to check for any additional components or attachments related to the columns before proceeding with the installation.
4. For large buildings, it is better to work based on a grid system rather than setting up each column individually. The framing should follow the established guidelines such as a sequence from 1 to 10 or 1 to 5. Furthermore, the necessary materials must be available on-site accordingly; otherwise, the work will be delayed.
5. Once the columns are in place, the next step is to install the rafters (for shed-type buildings) or the beams (for multi-story buildings).
During this process, all bolting must be executed accurately and with great care.
6. Step 3: Installation of Primary Members – Girts, Purlins/Sub-beams
7. After completing the framing work, purlins and girts must be set up for sheds and sub-beams must be set up for multi-story buildings.
8. Step 4: Setting up primary members pipes, bracing members, etc.
9. After the secondary members are in place, the bracing members and opening-related components must be set up.
10. Step 5: Setting up sheeting items wall sheeting and roof sheeting.
11. Work on sheeting items begins after the primary and secondary members have been set up.
12. For shed structures that include both wall and roof sheeting, the roof sheeting must be installed first. Any associated brickwork should also be completed. Subsequently, the height of the brickwork should be measured, and the remaining wall sheeting should then be installed.
13. When installing roof and wall sheeting, ensure that the overlapping is done carefully; otherwise, there is a risk of water leakage later on.
14. Fasteners must be installed with great care during the application of roof and wall sheeting; otherwise, the sheeting could come loose over time.
15. Generally, all buildings with roof sheeting require insulation; the insulation must be of high quality and installed correctly.
16. For walls, insulation is used in specific types of buildings such as cold storage facilities.
17. Step 6: Installation of accessory items trims, gutters, downpipes, canopies and soffits.
18. The installation of accessories follows the completion of the structural work; this must be carried out based on precise on-site measurements, otherwise, the components will not fit correctly.
19. Once feedback is received from the site, the trims, gutters, and downpipes must be fabricated according to the specified dimensions.
20. If the building includes a canopy or soffit, these must be installed. Finally, any doors, windows, ventilators or roof monitors should be installed.
Great care must be exercised while carrying out these tasks. Safety protocols must be strictly followed. Furthermore, these operations require such high precision that a deviation of even a few millimeters can lead to significant complications or necessitate the production of replacement materials.